How I Eliminated $200K in Procurement Waste
From Blank Checks to Controlled Purchasing
Role:Project Lead / Process Architect
Project Type: Procure-to-Pay Re-Engineering
Focus Areas: Finance Operations · Field Operations · Vendor Management · ERP Configuration
Systems: ComputerEase ERP | Impact: $200K Annual Waste Eliminated
The Challenge:
Field crews could request a PO with little information and make purchases without consistent approval or documentation. This made it difficult to understand what was being purchased, why it was purchased, or whether the purchase matched what was ultimately delivered.
The problems showed up across the organization:
-
No purchasing controls
-
Duplicate purchases and invoice errors
-
Poor visibility into job costs
-
Field crews losing time due to poor material planning
-
Accounting buried in reconciliation work
The financial waste was visible, but I found that the underlying problem wasn't simply spending. The process itself needed to be redesigned.
The Goal
I focused on four outcomes:
-
Build a structured procure-to-pay process
-
Eliminate unnecessary spending
-
Deliver accurate job-cost data
-
Get field crews the right materials faster
This meant changing both the system and how people worked within it, not just introducing another policy.
MY Role
I led the project end-to-end. That meant designing the process, configuring the ERP system, and most importantly, getting the field crews to actually use it. I reported to the CEO and CFO, but my real partner was the field manager Chris. Without his buy-in, nothing would stick.
What I Led
I approached the project in four phases:
Discover
I mapped the existing purchasing process from beginning to end and spoke with stakeholders across leadership, accounting, and field operations. The goal was not just to document what people were doing. I wanted to understand why the problems were happening and where the process was breaking down.
Design
I designed a procurement model that separated stock items from direct purchases and introduced a three-way matching process: PO → Receiver → Invoice. This gave Accounting a much stronger way to validate purchases and reduced manual reconciliation.
Build
I helped establish the company's first item master using vendor part numbers in ComputerEase. I also worked through system configuration, tax codes, approval logic, workflows, item setup, and purchasing controls. When I found a tax configuration bug (local rates were not linked to state rates), I diagnosed the issue and fixed it alongside our system admin rather than just reporting it.
Lead the Change
The process would not succeed if the field did not adopt it. I partnered with field leadership to roll out the new process, created SOPs, conducted training, and worked through resistance from crews.
I stopped pushing the form and started pushing the purpose. I showed crews that the $200K waste was money that could fund raises and equipment. Then I partnered with Chris to make receiver submission part of their weekly meeting structure, so accountability came from their own team, not from the office.
Outcome
The numbers:
-
$200,000 annual waste eliminated
-
100% of POs now require a documented quote
-
70% less time spent on invoice reconciliation
-
90%+ receiver compliance within 60 days
The bigger wins:
-
The company has reliable job-costing data for the first time
-
Vendors get paid accurately and on time
-
Field crews stopped seeing it as "my process" and started seeing it as "how things work"
-
A scalable foundation for future growth
What I Learned
Before this project, I assumed a well-designed process would sell itself. I was wrong. The three-way match was technically sound, but the field crews did not care about technical soundness. They cared about their time and their pay.
Adoption is not about enforcement. It is about framing. When I connected the change to something they actually cared about, raises and equipment, resistance turned into ownership. The workflow did not change. The framing did.
I also learned to verify system configurations before go-live. A broken tax table can silently undermine the whole process.
Sector: Commercial Construction
Engagement: 60-day process rollout
Service: Operational Transformation
$200K
Annual waste eliminated (Phase 1)
Eliminating $175-500K in annual procurement waste for a $30M commercial contractor
90%
Field Receiver compliance within 60 days.
70%
Estimated invoice reconciliation time reduced
A $30M commercial contractor had uncontrolled "blank check" purchasing by field crews, generating an estimated $500K in annual waste from duplicate buys and invoice errors. There was no reliable job costing because invoices never matched POs, and field crews were wasting hours waiting at vendors for unplanned material runs.
Mapped the existing purchasing process end-to-end and conducted discovery sessions with the CEO, CFO, and field teams to identify root causes. Designed a hybrid procure-to-pay model with stock items vs. direct POs and mandatory 3-way matching (PO, Receiver, Invoice). Built the company's first item master using vendor part numbers in ComputerEase, configured tax codes, and created SOPs for both field and office teams. Co-led the rollout with field management, addressing resistance by connecting the process to financial outcomes crews actually cared about. Managed scope creep by phasing the rollout and locking Phase 1 before expanding to service work.
$175K in annual waste eliminated. 90%+ field compliance on receiver submissions within 60 days. Invoice reconciliation time reduced by an estimated 70%. The company now has its first reliable job-costing data and a scalable procurement foundation built for future growth. CEO: "This is the guardrail we needed. You turned chaos into control." Field Manager: "You made the paperwork make sense to my guys. They finally see it as helping them, not hassling them."